On a GSM (or any other Telecom) site there are some activities in which Civil Works team is either fully involved or at least participated (or represented) in the activity. Those activities in which civil works is only represented is basically the one which have ownership with other departments. But due to some sort of support work or participation is required from civil works, so it has to spare its resources for those activities.
1. Technical Site Survey (CW+SA+RF+Transmission) (Normally owned by Site Acquisition )
2. Work Package Approval (Process is owned by Design Department or by CW if design is totally externalized/outsourced)
3. Site Kick off (The process is owned by Site Acquisition, however this is the activity in which site location is handed over from Site Acquisition to Civil Works, so in order to rule out the waste of money time and resources and chances of not meeting the target, at some later stage, CW representative has to take necessary measure. He/She has to mark all area which will be included in Construction, has to clearly tell site owner if any destruction is required, estimated time of construction etc.etc. )
4. Excavation + Layout + Lean concrete (Complete CW Activity)
5. Concrete Pouring (Pad + Columns) (Complete CW Activity)
6. Backfilling + Top slab concreting (Complete CW Activity)
7. Boundary wall (Complete CW Activity)
8. Tower Erection + Accessories installation (Complete CW Activity )
9. Generator installation & commissioning (Complete CW Activity)
10. AC Power Inspection (Power Meter+ ACDB+ Intake box) (Complete CW Activity)
11. Shelter or Sunshade Installation and (if applicable) Guardroom Installation (Complete CW Activity)
12. Declaring site RFI (Ready for Installation) (Complete CW Activity, The activity is important in a sense that normally time from Kickoff to RFI is an important KPI among other indicators. This is because during this time only civil works department can do work on site and is considered one of the main bottle necks in such projects. Once the site is declared RFI other teams of project like Telecom Implementation, BSS, Care can also do their due work on site along with other minor civil works which are being carried out on site. )
13. Finishing Works (Complete CW Activity)
14. Red – Line/As – Built Drawings preparation (Complete CW Activity)
15. Acceptance from Customer (The activity is owned by project as a whole)