CW Milestones Part-3 – Site Kick off

After Work Package approval, a formal hand over meeting is being arranged by Site Acquisition department, called site kick-off. This is the first and most important step which counts towards start of construction works on site. Normally the participants of the Kick Off meeting includes
  • Site Acquisition(SA) Representative
  • CW representative
  • Actual Owner or his representative of leased property of site
  • CW Sub Contractor’s team lead/site supervisor (along with his team , with all measuring and marking tools)
CW representative have to understand that once s/he will have accepted the site at the time of kick-off, without any report, CW is going to be responsible