Saturday, 5 March 2011

CW Milestones Part-4 – Excavation, Layout and Lean concrete


When site is being kicked –off, the site becomes the responsibility of Civil Works. And the period between Kick-off and RFI becomes very crucial for maintaining overall project speed because during this time only one department (i.e. Civil Works) is working on site. For the telecom rollout projects,  this period normally becomes among major bottlenecks, if not handled or planned properly. And the sales and management team has to be thoroughly worked out this period and need to identify for any manageable (contract negotiation/finalization of subcontractors, Sub-con preparedness and their relative brainstorming and trainings in order to be synchronized with targets etc.)  and unmanageable constraints (like offshore supplies of masts or generators etc., shortage of construction material etc in market), before finalizing and sharing targets and deadlines with customers.
The first thing after kick-off a civil subcontractor has to do is to mark boundaries of site, and clear or demolish (if required) the things within parameters.

Saturday, 12 February 2011

CW Milestones Part-3 – Site Kick off

After Work Package approval, a formal hand over meeting is being arranged by Site Acquisition department, called site kick-off. This is the first and most important step which counts towards start of construction works on site. Normally the participants of the Kick Off meeting includes
  • Site Acquisition(SA) Representative
  • CW representative
  • Actual Owner or his representative of leased property of site
  • CW Sub Contractor’s team lead/site supervisor (along with his team , with all measuring and marking tools)
CW representative have to understand that once s/he will have accepted the site at the time of kick-off, without any report, CW is going to be responsible